The cost impact of a compensation event is based upon the effect the event has on the cost of work already done and the forecast cost of work not yet done at the dividing date, which is often when the project manager instructed the change to the scope.
NEC3 and NEC4 can be used during the entire project life-cycle; from planning, defining legal relationships and procurement of works, all the way through to project completion, FM or asset maintenance, and beyond. The intended outcome of NEC3 contracts is that time and money performances are improved while increasing standards by encouraging collaborative working in order to achieve shared project objectives. This philosophy promotes a less adversarial approach, decreasing the chance and impact of costly disputes.
Most NEC4 contracts have nine core clauses which follow the list below from the ECC:
- General terms
- The Contractor's main responsibilities
- Time
- Quality management
- Payment
- Compensation events
- Title
- Liability and insurance
- Termination
The benefit of the NEC4 DBO contract is that it combines the responsibilities for design, construction, operation and/or maintenance, which can be procured from a single supplier. The DBO contract can therefore include a variety of services during construction and these works are completed.
The contractor and project manager should notify each other, as soon as practicable, of any matter which could affect the cost, completion, progress or quality of the works (in the ECC).
This contract should be used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
This contract should be used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
It is suitable for procuring a diverse range of works, services and supply, spanning major framework projects through to minor works and purchasing of supplies and goods. The implementation of NEC3 contracts has resulted in major benefits for projects both nationally and internationally in terms of time, cost savings and improved quality.
This is a secondary Option available in a number of NEC3 and NEC4 contracts. These allow for additional conditions of contract to that in the printed form – this could comprise of additions, deletions or omissions. Careful consideration should be given to the need for a Z clause. Care should also be taken to ensure that the clause retains the clarity, style and terminology of the rest of the contract as well as that it does not cause conflict with other clauses.
The cost impact of a compensation event is based upon the effect the event has on the cost of work already done and the forecast cost of work not yet done at the dividing date, which is often when the project manager instructed the change to the scope.
NEC3 and NEC4 can be used during the entire project life-cycle; from planning, defining legal relationships and procurement of works, all the way through to project completion, FM or asset maintenance, and beyond. The intended outcome of NEC3 contracts is that time and money performances are improved while increasing standards by encouraging collaborative working in order to achieve shared project objectives. This philosophy promotes a less adversarial approach, decreasing the chance and impact of costly disputes.
Most NEC3 contracts have nine core clauses which follow the list below from the ECC:
- General terms
- Contractor's main responsibilities
- Time
- Testing and Defects
- Payment
- Compensation events
- Title
- Risk and insurance
- Termination
To support constructive relationships, for example in collaborative based arrangements, these are often set at or close to zero.
The contractor and project manager should notify each other, as soon as practicable, of any matter which could affect the cost, completion, progress or quality of the works (in the ECC).
This contract should be used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
It is suitable for procuring a diverse range of works, services and supply, spanning major framework projects through to minor works and purchasing of supplies and goods. The implementation of NEC3 contracts has resulted in major benefits for projects both nationally and internationally in terms of time, cost savings and improved quality.
This is a secondary Option available in a number of NEC3 and NEC4 contracts. These allow for additional conditions of contract to that in the printed form – this could comprise of additions, deletions or omissions. Careful consideration should be given to the need for a Z clause. Care should also be taken to ensure that the clause retains the clarity, style and terminology of the rest of the contract as well as that it does not cause conflict with other clauses.